Senator Tim Kaine gives update on Creeper Trail reconstruction
Kiewit has installed 19 of 24 temporary bridges as repairs continue on the trail, officials said.
3 Articles
3 Articles
Creeper Trail reconstruction on track for late 2026 completion
Work to reestablish the damaged 18-mile portion of the Virginia Creeper National Recreation Trail between Damascus and Whitetop is expected to be completed by the end of this year, officials said Tuesday.
Senator Tim Kaine gives update on Creeper Trail reconstruction
DAMASCUS, Va. (WJHL) - United States Senator Tim Kaine (D-VA) held many events in Southwest Virginia Tuesday afternoon to celebrate funding for community projects, including the Creeper Trail reconstruction. Kaine stopped by Damascus Town Park to provide updates on the Creeper Trail reconstruction. The Creeper Trail was damaged in late 2024 by Hurricane Helene. Kaine [...]