Senai-Desaru Highway Upgrade Project Now 53.19% Progress, Expected to Be Completed in April 2027

Minister of Works (KKR), Datuk Seri Alexander Nanta Linggi confirmed that the Senai–Desaru Expressway (SDE) upgrade project has achieved 53.19% progress as of January 15, 2026. “Based on the site progress report as of January 15, 2026, this project has shown very encouraging performance. Actual physical progress has reached 53.19% completion, which is 0.02% ahead of schedule. This reflects the level of project management and good on-site coordin…
DisclaimerThis story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.Cross Cancel Icon

1 Articles

Minister of Works (KKR), Datuk Seri Alexander Nanta Linggi confirmed that the Senai–Desaru Expressway (SDE) upgrade project has achieved 53.19% progress as of January 15, 2026. “Based on the site progress report as of January 15, 2026, this project has shown very encouraging performance. Actual physical progress has reached 53.19% completion, which is 0.02% ahead of schedule. This reflects the level of project management and good on-site coordin…

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • There is no tracked Bias information for the sources covering this story.

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Paul Tan's Automotive News broke the news in on Friday, January 23, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)
News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal