Power Grid Brakes Wind Turbine Construction
Summary by 17:30live Rheinland Pfalz/Hessen
1 Articles
1 Articles
Rhineland-Palatinate has been lagging behind its own targets for the expansion of wind and solar energy for years. A central reason: the electricity grids. In many regions they are already used up – new green electricity can often no longer be absorbed. The problem is currently evident in the West Palatinate. In this field in Mehlingen, three wind turbines are supposed to be created. 15,000 households could thus be supplied with green electricit…