Data Centre Firms Say the AI Bottleneck Is Now Power and Labour

A survey of 300 decision-makers found power availability and skilled workers are the main barriers, with European grid delays stretching to 10 years.

Summary by TNW
Executives from NTT Data, Brookfield and Infosys say electricity and skilled labour, not chips, now limit how fast AI data centres get built. In Europe the binding constraint is worse, with grid connections in congested markets running to ten years. The thing slowing the AI buildout is no longer the chips. Executives running some of […] This story continues at The Next Web

5 Articles

Crypto BriefingCrypto Briefing
Reposted by
Cryptocurrency News | Cryptocurrency Prices | Market CapCryptocurrency News | Cryptocurrency Prices | Market Cap

Data center firms say energy and labor, not chips, are holding back AI growth

The AI industry's growth is hindered by energy and labor shortages, potentially leading to increased operational costs and delayed advancements.

Access to electricity and the shortage of skilled workers are emerging as the main obstacles to building data centres at the pace required by the expansion of artificial intelligence.

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 50% of the sources lean Left, 50% of the sources are Center
50% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Bloomberg broke the news in New York, United States on Tuesday, October 13, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal