Saipem Marks Neptun Deep Offshore Installation Milestone in Black Sea

The project remains on track for first gas in 2027 as the offshore platform and 160 km pipeline are completed, Reuters reported.

  • On Monday, OMV Petrom and Romgaz completed installation of the Neptun Alpha production platform in the Black Sea, keeping the Neptun Deep project on schedule for 2027 production startup.
  • The Saipem 7000, the world's third-largest semi-submersible crane vessel, lifted the 16,500-ton platform into position in 120 meters of water, anchoring it with 8 steel piles.
  • Crews finished the 160 km pipeline to Tuzla and completed 6 of 10 development wells, with the pipeline constructed from steel segments measuring 30 inches in diameter.
  • The platform is "fully automated and can be operated remotely," said Cristian Hubati, member of the Directoratului OMV Petrom responsible for Exploration and Production, supporting a 75% production increase.
  • Project teams will now focus on connecting subsea infrastructure and integrating offshore installations with the transport pipeline, followed by rigorous testing to prepare for 2027 production.
Insights by Ground AI

17 Articles

Right

Romania's interim prime minister, Ilie Bolojan, announced, on Tuesday morning, the completion of the installation of the production platform for the exploitation of natural gas in the Black Sea, stressing that it is the largest natural gas exploitation project in Romania.

Center

OMV Petrom and Romgaz have completed the installation of the offshore production platform for Neptun Deep, marking one of the most important stages in the development of the largest natural gas project in Romania, which is maintained in the graph for the start of production in 2027, is shown in a communication of the company.

·Bucharest, Romania
Read Full Article

The offshore production platform was installed in the Black Sea OMV Petrom, the largest integrated energy producer in South-Eastern Europe, and SNGN ROMGAZ SA, the largest producer and main supplier of natural gas in Romania, have completed the installation of the offshore production platform for Neptun Deep, marking one of the most important stages in the development of the largest natural gas project in Romania. The project remains in the grap…

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 50% of the sources are Center
50% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

ZF.ro broke the news in Ilfov County, Romania on Monday, July 20, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal