Grid access in Britain is now a priced commodity, not a free option.Key takeawaysOfgem launched a consultation on July 29, 2026 proposing a commitment fee of £237,500 to £712,500 per megawatt for large data centre projects accepting a UK grid connection offer, with the fee forfeited if projects exit the queue early.The UK grid connection queue has tripled in under a year, from 41 GW to 125 GW, with data centres claiming roughly 73 GW of that cap…
This story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.