To Notre-Dame, Donations Well Used and Little Reimbursed by the State: the Court of Auditors Welcomes the Reconstruction
10 Articles
10 Articles
The judges give a total satisfaction to the conduct of the work for five years.
In its last report on the cathedral's construction site, published on Wednesday, September 3, the institution highlights deadlines and a respected budget, while pointing to doubled operating costs and expressing some grievances.
In a report, magistrates stress the effectiveness of the public institution created on occasion, Rebuilding Notre-Dame de Paris, and support the establishment of a museum dedicated to the cathedral within the Hôtel-Dieu.
The Court of Auditors' report on Notre-Dame de Paris congratulates the managed management of the €843 million in donations for this exceptional construction site. But nine months after the reopening of the cathedral, challenges remain to come.
April 2024: the repair works of Notre-Dame Cathedral in Paris are in full swing. The delivery date is in all minds since the construction site is to be completed on 8 December. However, the diagnosis of the transept and roses of the cathedral, an operation planned before the fire, has still not been carried out. While the scaffolding is still in place, it is necessary to quickly decide on its dismantling, because the temporary work might be indi…
Notre-Dame de Paris: An exemplary project, without budget overruns or delays. The Court of Auditors praised the restoration of Notre-Dame de Paris this Wednesday, deeming it a "success": no additional costs, a perfectly controlled budget of €552 million, and deadlines met. An extraordinary project, financed by €843 million in donations from around the world. Published on 09/04/2025 at 11:01 Zen reading The titanic restoration project of Notre-Da…