New Jersey Data Center Fined More than $1M over Air Pollution Violation
The state says the generators violated air pollution law, and the company must get permits or stop operations.
On Tuesday, the New Jersey Department of Environmental Protection fined DataOne $1.07 million for installing and operating 62 large natural-gas generators in Vineland without required permits.
State inspectors discovered the generators during a July 29 site visit; they were absent during a December 2025 inspection, violating the Air Pollution Control Act.
A DataOne spokesperson told NBC10 the company disagrees with the determination but will apply for air permits and transition to "low-emission, quiet fuel cells" as the permanent solution.
Regulators ordered DataOne to obtain permits within 45 days or cease operations, as New Jersey Governor Mikie Sherrill emphasized the state's commitment to holding data centers accountable.
Sherrill signed laws this year regulating the industry's environmental impact, mirroring efforts in California and Texas to limit data center expansion and resource consumption.