Google and Environmental Group to Question Hydro-Quebec Consultants on Data Centres
The utility says the new rate would average 13 cents per kilowatt-hour, about twice what large-power data centres pay now.
Lawyers representing Google and an environmental coalition concluded questioning Hydro Quebec consultants on Thursday as the first part of a public hearing on proposed data-centre electricity rate hikes wrapped.
Hydro Quebec proposes raising energy prices to an average of 13 cents per kilowatt-hour for data centres requiring more than five megawatts of power, aiming to protect residential customers from surging costs driven by artificial intelligence demand.
Google lawyer Adina Georgescu challenged whether consultant Dunsky provided meaningful comparisons between markets, citing Virginia's more than 600 operating facilities versus roughly 20 in Quebec requiring significant power capacity.
Consultant Alexis Renaud-Bezot acknowledged his firm had not "systematically" examined how rates were calculated in other jurisdictions, though Hydro Quebec claims the 13-cent rate remains "competitive" with Ontario and Nova Scotia.
Industry experts project data-centre electricity demand across North America could increase 133 per cent by 2030, positioning Hydro Quebec's approach as a model most utilities are expected to adopt to protect existing customers.