Vineyard Wind says GE Vernova must keep working on the project and pay damages after a 2024 blade collapse delayed construction nearly two years.
- Vineyard Wind filed a lawsuit against GE Renewables after the latter tried to terminate contracts for turbine services and maintenance.
- GE Vernova claims Vineyard Wind owes it $300 million, while Vineyard Wind says GE Renewables owes it $545 million due to a turbine blade collapse and delays.
- The lawsuit states that allowing GE Renewables to back out would cause irreparable harm, as it is the only company able to perform the remaining work.
Insights by Ground AI
16 Articles
16 Articles
+12 Reposted by 12 other sources
Developer of Massachusetts offshore wind farm sues to stop turbine manufacturer from walking away
The developer of a major Massachusetts offshore wind farm is suing its turbine manufacturer seeking to force it to stay with the project.
·United States
Read Full ArticleCoverage Details
Total News Sources16
Leaning Left3Leaning Right4Center8Last UpdatedBias Distribution53% Center
Bias Distribution
- 53% of the sources are Center
53% Center
L 20%
C 53%
R 27%
Factuality
To view factuality data please Upgrade to Premium