Coatbridge skyline changing as Jackson Court tower demolition enters major new phase
By the end of February, the tower is expected to appear almost at ground level to passers-by, with the remainder of the structure anticipated to be down within the next four to six weeks.
Demolition of Coatbridge tower progresses
WORK to demolish Coatbridge’s 172-foot Jackson Court tower is progressing, North Lanarkshire Council has said. By the end of February, the tower – built in 1971 – is expected to be almost at ground level, with the remainder of the structure anticipated to be down within the next four to six weeks. The project faced early structural challenges, but after detailed planning a new approach was put in place. One end of the building was taken down fl…