Cost of data center power project rises, but won’t affect customers, Minnkota says
Applied Digital will cover the full expense as Minnkota cites a fall deadline, scarce materials and tariffs for the 45% increase.
Summary by KVRR Local News
4 Articles
4 Articles
+3 Reposted by 3 other sources
Cost of data center power project rises, but won’t affect customers, Minnkota says
FARGO — The cost of the powerline and substation needed by a data center north of Fargo has risen from $75 million to $110 million, but developers say the data center company will still cover the entire cost of the project. Applied Digital needs the project to power its data center being built between Fargo and Harwood. The data center requires 280 megawatts of power at peak demand. Applied Digital will pay for the project but it will be owned b…
Coverage Details
Total News Sources4
Leaning Left0Leaning Right3Center1Last UpdatedBias Distribution75% Right
Bias Distribution
- 75% of the sources lean Right
75% Right
C 25%
R 75%
Factuality
To view factuality data please Upgrade to Premium