Constructora Completes Works in Hospital De Linares with 30% Advance
Summary by vlnradio.cl
1 Articles
1 Articles
As part of the construction of the Linares Hospital, the Maule Health Service has reported that, on 1 July 2025, the company Astaldi has notified the end of its main activities. 30.43% of the original contract is fulfilled and progressed.This deadline is due to a commitment made in September 2024, where the execution of works marked out with defined items within nine months and, among other aspects, the term of common agreement of the contract a…