DESRI and El Paso Electric Announce Start of Construction at Santa Teresa Solar & Storage Facility in Doña Ana County, NM
DOÑA ANA COUNTY, NEW MEXICO, JUL 14 – The project features a 150 MW solar plant and 600 MWh battery system to provide clean energy for 60,000 homes and enhance grid reliability under a 20-year agreement.
- On July 14, 2025, DESRI and El Paso Electric initiated construction on a 150 MWac solar and 600 MWh battery storage facility located in Doña Ana County, New Mexico.
- The project followed the Carne solar and storage project that started construction in 2024 and secured financing from a consortium including DNB Bank ASA and National Bank of Canada.
- The Santa Teresa project features a 600 MWh battery storage system and a 150 MW solar facility in Doña Ana County, New Mexico, operating under a two-decade energy supply contract with El Paso Electric to deliver renewable power to roughly 60,000 homes annually.
- Hy Martin, DESRI's Chief Development Officer, described the Santa Teresa Project as a key element in DESRI’s expanding collaboration with El Paso Electric, highlighting its role in enhancing grid reliability, advancing clean energy initiatives, and supporting economic development in Doña Ana County.
- The project supports rising energy demand by delivering clean energy and added capacity that strengthens regional reliability and sustainability while advancing economic development.
28 Articles
28 Articles
New 150-Megawatt Solar Power Plant For New Mexico
The leading renewable energy developer DESRI is behind a new 150-megawatt solar power plant in New Mexico, which will also send clean kilowatts into Texas, too. The post New 150-Megawatt Solar Power Plant Greenlighted For New Mexico (And Texas) appeared first on CleanTechnica.

DESRI and El Paso Electric Announce Start of Construction at Santa Teresa Solar & Storage Facility in Doña Ana County, NM
/PRNewswire/ -- DESRI, in partnership with El Paso Electric (EPE), today announced that the Santa Teresa Solar and Storage project (Santa Teresa, or the...
DESRI and El Paso Electric Break Ground on 150 MW Solar and Storage Project in New Mexico
DESRI, in collaboration with El Paso Electric (EPE), has announced the start of construction on the Santa Teresa Solar and Storage project after reaching financial notice to proceed (FNTP). Located […] The post DESRI and El Paso Electric Break Ground on 150 MW Solar and Storage Project in New Mexico appeared first on SolarQuarter.
Construction starts on New Mexico solar + storage project that uses American BESS
DESRI has started construction on the Santa Teresa Solar and Storage project in Doña Ana County, New Mexico, for El Paso Electric (EPE). The 150-MW solar, 600-MWh storage project is the second project DESRI is working on for EPE. The developer began construction on Carne, a 130-MW solar, 260-MWh storage project, last year. “The Santa Teresa Project… The post Construction starts on New Mexico solar + storage project that uses American BESS appear…
Coverage Details
Bias Distribution