Construction of new water tower in Detroit Lakes is on schedule and on budget

DETROIT LAKES — The new Detroit Lakes water tower now under construction is slightly ahead of schedule, according to Detroit Lakes City Engineer Jon Pratt. Construction work on the steel tank should be finished in the next week or so, he said. As of last week, the tank was about two-thirds done, with one more 10-foot section yet to be attached and welded. The steel bowl is being welded together on-site. An independent company will then check th…