A Lot of North A0 Is Close to the Final Reception, but Will Not Be Given in Circulation Yet
4 Articles
4 Articles
Works on Lot 4 of the A0 North Highway, on the Pantelimon – Glina section, are approaching reception, with the Romanian manufacturer UMB Spedition reaching a physical stage of about 99%.
This is the 4 Pantelimon – Glina lot of the A0 North motorway, which is close to reception at the end of the works. The Romanian manufacturer UMB Spedition prepares for reception on the entire 4.47 km lot. On the yard are currently making the last works of mounting some pipes for draining water and applying the layer of anti-corrosive protection on concrete elements from the bridge over Lake Cernica (1.3 km), the most complex structure on this l…